8/16/2022 Update (REVISED) - Continued Concrete Paving - Shenandoah Dr

For best viewing, please visit this website on a computer rather than a mobile device.

Previously, it was posted that Winchester Pass was going to be closed for a week starting 8/22. This is no longer the case. With our continued paving on Stonecrest Rd, we are scheduled to be at Shenandoah Dr by Monday, 8/22. Shenandoah Dr will not be fully closed, as it is the only access to that neighborhood. However, Shenandoah Dr will be restricted in width, so that it can be paved in halves. Please be cautious when driving through the Shenandoah/Stonecrest intersection.

Please continue to plan for delays up to 20 minutes over the next several weeks as we continue to pave the West half of Stonecrest Road.

 

As always, we appreciate your understanding as we work to improve the quality of Stonecrest Road as quickly and safely as possible.

If you have driveway access constrains and/or need wider driveway access on a given date, please email us a few days in advance at stonecrest@ddmcc.net so that we may accommodate you as best as we can.

8/2/2022 Update - Forest Trail Closure! (REVISED)

For best viewing, please visit this website on a computer rather than a mobile device.

Starting Monday (8/8), Forest Trail will be closed for concrete paving on Stonecrest Road. Winchester Pass will be kept open at full-width to allow for access to and from the Settlement neighborhood. Forest Trail will be re-opened to traffic by Tuesday of the following week (8/16) after the concrete reaches the appropriate cure strength for traffic. 

Please continue to plan for delays up to 20 minutes over the next several weeks as we continue to pave the West half of Stonecrest Road.

 

As always, we appreciate your understanding as we work to improve the quality of Stonecrest Road as quickly and safely as possible.

If you have driveway access constrains and/or need wider driveway access on a given date, please email us a few days in advance at stonecrest@ddmcc.net so that we may accommodate you as best as we can.

7/26/2022 Update - Paving Start

For best viewing, please visit this website on a computer rather than a mobile device.

Starting tomorrow (7/27) concrete paving will begin on Stonecrest Road at FM 407 heading South. As we pave through, several leave-outs will be left at driveways and side streets.

 

Please note that during concrete paving, traffic delays are to be expected as the concrete trucks must briefly stop in the lane of traffic to dump the concrete in front of the paving operation. During the next 5-6 weeks, please give yourself an extra 20 minutes of travel time, should you get stopped on Stonecrest during the paving operation.

Next week, Forest Trail will be closed to all traffic as we concrete pave through that intersection. Winchester Pass will be kept open at full-width to allow for access to and from the Settlement neighborhood. After a week of concrete being placed, access at Forrest Trail will be re-opened. Similarly, as we approach Winchester Pass, notice will be provided on this website about when that will happen and Winchester Pass will be closed to traffic, leaving Forest Trail as the access point.

Due to Shenandoah Dr being the only access point to that neighborhood, it will be paved in halves so that access may always be kept to and from Shenandoah Dr.

 

As always, we appreciate your understanding as we work to improve the quality of Stonecrest Road as quickly and safely as possible.

If you have driveway access constrains and/or need wider driveway access on a given date, please email us a few days in advance at stonecrest@ddmcc.net so that we may accommodate you as best as we can.

7/19/2022 Update - Cem-Lime Operation & Paving Start

For best viewing, please visit this website on a computer rather than a mobile device.

We appreciate your patience with the traffic delays at the intersections. Today (Tuesday 7/19), crews are finishing the Shenandoah intersection. Tomorrow morning, from 7:00 am to 11:00 am, the intersection of Winchester Pass will be temporarily closed as crews stabilize the base, similar to Forest Trail last Friday.

The base stabilization process consists of crews removing the tie-ins (temporary driveway access), breaking up the soil and adding water, then mixing the Cem-Lime and compacting the base.  Once compaction and grades are set, crews re-establish the tie-ins (temporary access).

 

Paving will be starting next week! Check back Monday the 25th to see our projected paving schedule and how the intersections of Forest Trail, Shenandoah, and Winchester Pass will be affected.

 

As always, we appreciate your understanding as we work to improve the quality of Stonecrest Road as quickly and safely as possible.

7/13/2022 Update - Stonecrest Cem-Lime Operation Starts Tomorrow!

For best viewing, please visit this website on a computer rather than a mobile device.

Starting on Thursday, July 14th, and lasting through Friday, July 22nd, subgrade treatment with Cem-Lime will be taking place inside of the current road closure. Each day, different driveways will be affected briefly during the operation, due to subgrade treatment being required in front of all driveways. We will do our best to accommodate you as best as we can while working in front of your home or business.

As always, we appreciate your understanding in advance as we work to improve the quality of Stonecrest Road as quickly and safely as possible.

7/8/2022 Update - Stonecrest Closed to Thru Traffic

For best viewing, please visit this website on a computer rather than a mobile device.

Starting on Tuesday, July 12th, and lasting through Wednesday, July 13th, Stonecrest Rd will be closed to thru traffic, from FM 407 to Frenchtown Rd. Thru traffic will need to access Stonecrest via Frenchtown Rd.

 

Residents living between FM 407 and Frenchtown Rd will still have access to and from their homes. This closure is expected to only last a couple of days. At all times, Stonecrest will remain Southbound one-way traffic only.

 

See the image below for a visual of this closure.

6/25/2022 Update - Construction Has Begun!

For best viewing, please visit this website on a computer rather than a mobile device.

As you may have noticed, construction officially began on Stonecrest Road on Thursday, 6/23. We understand that the new traffic pattern was confusing at first to some, but rest assured we have taken additional measures to add traffic control signs ("WRONG WAY" and "ONE WAY" signs) at all side streets that intersect the Stonecrest closure to ensure traffic is always driving in the correct direction. As a reminder, Stonecrest Road is Southbound traffic only from FM 407 to Oak Ridge Ln. We are currently scheduled to keep traffic in this one-way Southbound orientation until the end of the year. During construction, we strongly encourage any cyclists and pedestrians to seek other paths for your safety, the safety of the traveling public, and the safety of our crews.

This website will be continually updated as things progress on the Stonecrest Rd project. If there are any questions, concerns, or requests, please contact DDM Construction (General Contractor) at stonecrest@ddmcc.net.

We know that construction can be an inconvenience at times. DDM Construction would like to thank you for your understanding and patience as we work to repair and improve the quality of Stonecrest Road.

6/1/2022 Update - Start of Construction

For best viewing, please visit this website on a computer rather than a mobile device.

In a couple of week, Stonecrest Road construction will begin. Starting June 23rd, Stonecrest Rd (between FM 407 & Oak Ridge Ln) will be one-way traffic only, flowing Southbound. Traffic will stay in this orientation for the duration of construction. The Detour Route to the North end of Stonecrest Rd will be US Hwy 377 to either Frenchtown Road, or to FM 407. Please see the image below giving a visual of traffic flow on Stonecrest Rd while construction is taking place.

Please note that access to private driveways, side streets, and business entrances will be kept at all times, minus one-off closures during active construction in front of those specific access points. Advanced notice will be given directly to these properties via handout a few days ahead of the closure. Please be on the lookout for these notices. 

This website will be continually updated as things progress on the Stonecrest Rd project. If there are any questions, concerns, or requests, please contract DDM Construction (General Contractor) at stonecrest@ddmcc.net. Any emails received here will be acknowledged in a timely manner.

 

DDM Construction would like to thank you in advance for your understanding as we work to repair and improve the quality of Stonecrest Road.

Southbound Traffic Map.jpg